Didsbury Landfill - Phase V Construction
       
     
Didsbury Landfill - Phase V Construction

Client: Mountain View Regional Waste Management Commission

Consultant: Tagish Engineering (Red Deer, AB)

Start Date: March 2014

Completion Date: April 2014

Project Scope:

  • Excavate +/- 60,000 m³ future class II landfill cell

  • Supply and install leachate collection system, including perforated leachate collection pipes, wash rock, geotextile wrap, and manholes

  • Installation of a 600 mm thick clay liner

  • Installed +/- 12,000 sq. ft. 80 mil SDPE liner, including cleaning and fusing to existing liner

  • Install tire shred drainage layer and filter geotextile