Client: City of Camrose
Consultant: WSP
Start Date: August 2020
Completion Date: October 2020
Project Scope:
Excavate, haul and stockpile ~11,000 m³ of topsoil and subsoil
Excavate, haul and stockpile ~20,000 m³ common material
Import and place ~5,000 m³ clay material from borrow
Install ~20,000 m³ compacted clay liner and clay liner end slopes including subgrade preparation
Supply and place perforated and non-perforated HDPE leachate collection pipe including geotextile and drainage rock
Supply and install leachate collection manholes and associated fittings
Load, haul and place ~14,000 m² of tire shred drainage layer
Load, haul and place approximately 1 meter thick garbage frost cover layer
Supply and install 7 each 500 mm CSP drainage culverts
Install a recycled concrete equipment access road including approaches
Installed recycled concrete burn pits