Didsbury Landfill - Cell VI Construction and Class III Cell Capping    Client:  Mountain View Regional Waste Management Commission   Consultant:  Parkland Geo-Environmental Ltd.   Start Date:  April 2016   Completion Date:  July 2016   Project Scop
       
     
20160526_132839.jpg
       
     
20160623_113055.jpg
       
     
20160623_113003.jpg
       
     
20160628_123144.jpg
       
     
20160720_133024.jpg
       
     
20160720_133028.jpg
       
     
20160719_113635.jpg
       
     
20160623_112940.jpg
       
     
20160810_140821 (2).jpg
       
     
  Didsbury Landfill - Cell VI Construction and Class III Cell Capping    Client:  Mountain View Regional Waste Management Commission   Consultant:  Parkland Geo-Environmental Ltd.   Start Date:  April 2016   Completion Date:  July 2016   Project Scop
       
     

Didsbury Landfill - Cell VI Construction and Class III Cell Capping

Client: Mountain View Regional Waste Management Commission

Consultant: Parkland Geo-Environmental Ltd.

Start Date: April 2016

Completion Date: July 2016

Project Scope:  

Part One: Cell VI – Construction

  • Excavated and stockpiled topsoil, clay and other native soil from Cell VI – 30,000 m³

  • Excavated and disposed of municipal solid waste from Cell VI – 5300 m³

Part Two: Cell VI – Liner System

  • Subgrade prep to 150 mm depth at 100% SPMDD – 22,550 sq.m

  • Clay liner 600 mm thick at 98% SPMDD at 2-4% above optimum MC – 22,550 sq.m

  • 80 mil HDPE liner supply and install, includes cleaning and fusing to existing liner – 22,550 sq.m

  • Liner protection geotextile supply and install – 22,550 sq.m

Part Three: Cell VI Leachate Collection System

  • Supplied and installed perforated PVC leachate pipe, including washed rock and geotextile wrap – 250 lm

  • Supplied and installed 150 mm solid PVC leachate trunk line along eastern edge to new manhole; included operator valve, tied into existing manhole, trenching, backfill and associated works – 40 lm

  • Supplied and installed new leachate collection manhole; Includes excavation, backfill, operator valve, clean out wye with pipe, suction pipe, fittings and other associated works

  • Placed tire shred drainage layer - 450 mm thickness – 21,400 sq.m

  • Supplied and installed tire shred filter geotextile layer – 21,400 sq.m

Part Four: Cell VI Subdrains

  • Supplied new subdrain manhole

  • Installation of subdrain manholes, includes excavation, backfill, gravel base pad and associated works

  • Supplied and installed eastern and western subdrains. Includes trench excavation, backfill, drainage rock and geotextile wrap – 210 lm

Part Five: Cell VI Roads

  • Strip and salvage existing gravel

  • Subgrade prep to 150 mm depth at 100% SPMDD – 2575 sq.m

  • Installed salvaged gravel as sub-base, supplied and installed sub-base gravel, Supply and install base gravel – 2575 sq.m

Part Six: Class III Cell Capping

  • Subgrade grading – 20,900 sq.m

  • Clay cap placement 600 mm thick at 98% SPMDD at 2-4% above optimum moisture content – 12,540 m³

  • Subsoil placement 350mm thick at 95% SPMDD – 7320 m³

  • Topsoil placement 200 mm thick – 4180 m³

  • Seeding – 20,900 sq.m

20160526_132839.jpg
       
     
20160623_113055.jpg
       
     
20160623_113003.jpg
       
     
20160628_123144.jpg
       
     
20160720_133024.jpg
       
     
20160720_133028.jpg
       
     
20160719_113635.jpg
       
     
20160623_112940.jpg
       
     
20160810_140821 (2).jpg