Camrose Regional Landfill Cell 21     Client:  The City of Camrose    Consultant:  WSP / MMM Group    Start Date:  June 2017   Completion Date:  September 2017   Project Scope:     Excavate, haul and stockpile ~10,000 m³ of topsoil & subsoil
       
     
2.jpg
       
     
3.jpg
       
     
4.JPG
       
     
5.JPG
       
     
6.JPG
       
     
7.JPG
       
     
  Camrose Regional Landfill Cell 21     Client:  The City of Camrose    Consultant:  WSP / MMM Group    Start Date:  June 2017   Completion Date:  September 2017   Project Scope:     Excavate, haul and stockpile ~10,000 m³ of topsoil & subsoil
       
     

Camrose Regional Landfill Cell 21

Client: The City of Camrose

Consultant: WSP / MMM Group

Start Date: June 2017

Completion Date: September 2017

Project Scope:

  • Excavate, haul and stockpile ~10,000 m³ of topsoil & subsoil

  • Excavate, haul and stockpile ~15,000 m³ common material

  • Import and place ~15,000 m³ clay material from borrow

  • Install ~20,000 m³ compacted clay liner and clay liner end slopes including subgrade preparation

  • Supply and place perforated and non-perforated HDPE leachate collection pipe including geotextile and drainage rock

  • Supply and install leachate collection manholes and associated fittings

  • Load, haul and place ~26,000 m² of tire shred drainage layer

  • Load, haul and place ~26,000 m² of 1 meter thick garbage frost cover layer

  • Supply and install 300 mm to 500 mm CSP drainage culverts