Flood Damage Recovery and Erosion Protection - Millarville Racetrack
       
     
Flood Damage Recovery and Erosion Protection - Millarville Racetrack

Client: M.D. of Foothills

Consultant: AMEC Environment and Infrastructure

Start Date: August 2014  

Completion Date: October 2014

Project Scope:

  • Care of water and sediment control

  • Stream bank stabilization techniques

  • Including longitudinal stone toe protection

  • Installation of various erosion control and bio-engineering techniques

  • Top soiling and seeding

  • Supply and install bedding gravels

  • Supply and install debris clusters within riprap toe

  • Supply and install root wads within riprap toe

  • Supply, install and remove temporary bridge to Gaudet site

  • Armour an estimated 300 m of damaged river bank and install two 15 m key-ins to existing river banks