Client: The Town of High River

Consultant: Clifton Associates

Start Date: October 2017

Completion Date: July 2018

Project Scope:

  • Supply and place ~18,000 m³ of Class II/III riprap armour

  • Installation and removal of 525 lineal meters of river isolation

  • Installation and removal of ~65,000 m² bird deterrent netting

  • Excavate and stockpile ~8000 m³ of topsoil and subsoil

  • Excavate, haul, place and compact ~8000 m³ of common material

  • Import, place and compact ~4000 m³ of clay core fill material

  • Import and place granular drainage material

  • Supply and install ~7200 m² of gravel roads

  • Supply and install ~11,000 m² of turf reinforcement matting (TRM)

  • Placement of ~35,000 m² of topsoil & subsoil

  • ~3 hectares of field cultivation